Amstersdam AM7 Rack 0508 PDU Maintenance
Scheduled Maintenance Report for Tempest
Completed
The scheduled maintenance has been completed.
Posted Mar 14, 2024 - 09:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 14, 2024 - 05:00 UTC
Scheduled
IBX: AM7

DESCRIPTION: We hereby inform you that Equinix will perform a planned power migration to a new energy distribution section.
This migration is the final step in the expansion project of the existing power distribution of AM7.

The existing cable on the PDU will be removed and a newly installed cable from another power section will be installed.

This maintenance will cause a temporary service interruption on the primary or redundant electrical power supply(s) to your rack(s).

Expected duration is about 4 hours
Posted Feb 12, 2024 - 17:24 UTC
This scheduled maintenance affected: Europe (Amsterdam, Netherlands).